Kimbe Overseas Wharf
Client
Pacific Marine Group and PNG Ports
Location
Kimbe, Papua New Guinea
Services
Marine Structural Engineering, Mooring Analysis, Concept and Detailed Design
Key Project Benefits
-
Commercial wharf operations maintained during construction
-
Significant cost savings through temporary mooring arrangements
-
Improved constructability and quality above the tidal zone
Shoreline developed temporary mooring and alternative fender support designs for Kimbe Overseas Wharf, allowing commercial vessel operations to continue during construction. The solutions addressed operational constraints, improved constructability, and provided a more cost-effective approach to the works.
Scope of Works
-
Completed mooring analysis and designed a temporary steel dolphin to support ongoing commercial vessel operations.
-
Developed an alternative fender support arrangement using precast concrete elements.
-
Designed the precast fender support arrangement to allow construction activities above the tidal zone, improving constructability and construction quality.
-
Reduced operational disruption and supported more efficient construction delivery.